Overlay President's Circle
Description: Repair curb, gutter, and sidewalks, construct handicap curb cuts beginning May 29th. Remove old asphalt beginning week of June 18th. Overlay with 2 inches of new asphalt the week of June 18 and apply new street markings on President’s Circle from Creelman Street to Morrill Road. Alternate No. 2 as shown on the drawing below will not be done as a part of this project.
Constraints/Restrictions: Traffic will be directed around construction as it progresses.

This image is proportionally scaled as shown.
Click on the Image to see it a full scale.